Question: A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path

A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path is 125 days with a project standard deviation of 15 days, find the project deadline that gives this project a 23% chance of on-time completion. (Use NORMAL CURVE AREAS table in APPENDIX I of the textbook.)

Group of answer choices from

113.96 to 114.08 days from 113.84 to 113.96 days from 114.2 to 114.32 days from 113.72 to 113.84 days from 114.08 to 114.2 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!