Question: A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path

A project being analyzed by PERT has 55

A project being analyzed by PERT has 55 activities, 8 of which are on the critical path. If the estimated time along the critical path is 125 days with a project standard deviation of 15 days, find the project deadline that gives this project a 4% chance of on-time completion. (Use NORMAL CURVE AREAS table in APPENDIXI of the textbook.) O from 98.81 to 98.93 days O from 98.69 to 98.81 days from 98.93 to 99.05 days from 98.57 to 98.69 days from 98.45 to 98.57 days