Question: A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 81, the probability that the project will take 218 days or more to complete is what?
a. 0.0126
b. 0.8413
c. 0.6716
d. 0.3283
e. 0.1587