Question: A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path

A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 81, the probability that the project will take 218 days or more to complete is what?

a. 0.0126

b. 0.8413

c. 0.6716

d. 0.3283

e. 0.1587