Question: A project being analyzed by PERT has an expected time along the critical path of 90 days with a project variance of 25 days. What
A project being analyzed by PERT has an expected time along the critical path of 90 days with a project variance of 25 days. What is the probability that the project will be completed within 88 days?
Group of answer choices
0.5320
0.4680
0.3446
0.6554