Question: A project can be decomposed into 4 paths. Each path connects the starting activity to the ending activity. Their lengths of the paths are listed

A project can be decomposed into 4 paths. Each path connects the starting activity to the ending activity. Their lengths of the paths are listed below.
Path 1 length: 55 days
Path 2 length: 58 days
Path 3 length: 62 days
Path 4 length: 60 days
The minimum amount of time required to complete the ENTIRE project is how many days?