Question: A project can be decomposed into 4 paths. Their lengths are listed below. Path 1 length: 25 days Path 2 length: 23 days Path 3

A project can be decomposed into 4 paths. Their lengths are listed below. Path 1 length: 25 days Path 2 length: 23 days Path 3 length: 25 days Path 4 length: 24 days The minimum amount of time required to complete the entire project is how many days? 23 O 24 25 Question 3 3 pts Which statement regarding critical path and non-critical path is WRONG? O Critical path is the path with the highest number of activities. O Only non-critical path activity can have positive slack time. O Critical path determines the completion time of the project. O None of the above. O