Question: A project has four possible paths, as shown below with their associated path lengths. Paths Length ACF 9 weeks ACDF 1 2 weeks BDF 1

A project has four possible paths, as shown below with their associated path lengths.
Paths Length
ACF 9 weeks
ACDF 12 weeks
BDF 10 weeks
BEF 10 weeks
Every activity except activity A can be crashed for a cost given in the second table below.
Activity Crashable weeks $/week cost to crash
A 0-
B 2 $90
C 1 $100
D 3 $130
E 1 $80
F 1 $200
Determine the shortest length of time to complete the project after crashing by filling in the table below. The last 4 rows keep track of the length of each of the paths. For each Step (column): (i) in the 2nd row, enter the activity that is crashed in that step and the corresponding cost, and then (ii) enter the new path length for each path in the 4 cells below. (For example, if you crashed both B and C in Step 1(which is not correct), you would enter "B+C, $190" in row 2 for Step 1.) Note that the correct answer may not use all 7 Steps!
2. Determine the total cost for crashing the project: __________
(Remember, you should crash only 1 week at a time, so each column in the table below reduces the length of the project by exactly one week. See Topic 7b.)
Step 1 Step 2 Step 3 Step 4 Step 5 Step 6 Step 7
Path Initial length
ACF 9
ACDF 12
BDF 10
BEF 10

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!