Question: A project consists of five tasks: A , B , C , D and E . Task A must be completed before B and C

A project consists of five tasks: A, B, C, D and E. Task A must be completed before B and C are started, and task C must be completed before task D is started, and tasks B and D must be completed before task E can be started. Each task takes one day to complete. What is the duration of this project? (2 points)