Question: project consists of five tasks: A , B , C , D and E . Task A must be completed before B and C are
project consists of five tasks: A B C D and E Task A must be completed before B and C are started, and task C must be completed before task D is started, and tasks B and D must be completed before task E can be started. How many paths are in this network?