Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 5 - B
A project for improving a billing process has the following precedence relationships and activity times:
| Activity | Activity Time (weeks) | Immediate Predecessor(s) |
| A | 5 | - |
| B | 8 | - |
| C | 5 | A |
| D | 12 | B,C |
| E | 11 | B |
| F | 4 | D |
| G | 4 | E |
| H | 7 | F, G |
Choose the correct network diagram and calculate the slack for each activity. Which activities are on the critical path?
| Activity | Activity Time (weeks) | On Critical Path? | Slack (weeks) |
| A | 5 | Y/N? | ? |
| B | 8 | Y/N? | ? |
| C | 5 | Y/N? | ? |
| D | 12 | Y/N? | ? |
| E | 11 | Y/N? | ? |
| F | 4 | Y/N? | ? |
| G | 4 | Y/N? | ? |
| H | 7 | Y/N? | ? |