Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 4 B 9

A project for improving a billing process has theA project for improving a billing process has the

A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 4 B 9 8 A D 14 B, C mo W I E 9 B F 5 D G 3 E H 6 F, G b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Slack (weeks) A 4 B 9 8 D 14 E 9 5 G 3 6