Question: Question content area Part 1 A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate

Question content area

Part 1

A project for improving a billing process has the following precedence relationships and activity times:

Activity Activity Time (weeks) Immediate Predecessor(s)
A 4
B 10
C 8 A
D 12 B, C
E 9 B
F 4 D
G 3 E
H 9 F, G

Part 2

a. Choose the correct network diagram below.