Question: Question content area Part 1 A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate
Question content area
Part 1
A project for improving a billing process has the following precedence relationships and activity times:
| Activity | Activity Time (weeks) | Immediate Predecessor(s) |
| A | 4 | |
| B | 10 | |
| C | 8 | A |
| D | 12 | B, C |
| E | 9 | B |
| F | 4 | D |
| G | 3 | E |
| H | 9 | F, G |
Part 2
a. Choose the correct network diagram below.