Question: A project has 3 paths. You need to have this project completed in less than 4 weeks and have computed the following probabilities: Path Probability

A project has 3 paths. You need to have this

A project has 3 paths. You need to have this project completed in less than 4 weeks and have computed the following probabilities: Path Probability of completion in less than 4 weeks Critical Path 96% Non-critical Path 1 85% Non-critical Path 2 88% What is the probability the project will be completed in less than four weeks? Express your answer as a percentage, no decimal places, don't type the percent sign. (If your calculator says 0.6767, you would enter 68.)