Question: A project has 7 activities. The relationship between activities is as below: The duration of these activities and the labor requirement for the activities are
A project has activities. The relationship between activities is as below:
The duration of these activities and the labor requirement for the activities are as below:
The project duration should not exceed the minimum project schedule. Only three men are available for the project execution. Find the resource schedule with respect to labor.