Question: Q: 1 A project has 7 activities. The relationship between activities is as below: table [ [ Activity: , A , B , C

Q: 1 A project has 7 activities. The relationship between activities is as below:
\table[[Activity:,A,B,C,D,E,F,G],[Preceding Activity:,--,--,--,A,B,C,D]]
The duration of these activities and the labor requirement for the activities are as below:
\table[[Activity:,A,B,C,D,E,F,G],[Duration (Weeks):,1,2,2,1,3,2,1],[Labor Requirement:,2,1,1,1,Im,1,1],[1,,,,,,,]]
The project duration should not exceed the minimum project schedule. Only three men are available for the project execution. Find the resource schedule with respect to labor.