Question: A Project has an expected completion time of 18 weeks, and a Project Variance of 2.98 weeks. Calculate the Z Value that would be used
A Project has an expected completion time of 18 weeks, and a Project Variance of 2.98 weeks. Calculate the Z Value that would be used to determine the probability of completing the project in 20 weeks.