Question:
A project has an initial capital cost of $9.0M. The company use $0.85M from its retained earnings, and the rest of the funds will be raised through debt and equity as per the following capital structure:
•Debt Ratio: 0.35 (35%)
•Debt structuring: Loans 30%, and bonds
•Equity structuring:
Retained earning, preferred shares 35%, and common shares
Determine the funds that would be raised through debt (Loans and Bonds) and equity (Preferred & Common Shares)