Question: A project has been analyzed using the critical path method ( CPM ) . The time for comp determined to be 3 0 weeks. If

A project has been analyzed using the critical path method (CPM). The time for comp determined to be 30 weeks. If the time for one activity were reduced by 1 week (fror best describes how the project completion time will be impacted?
If the activity is NOT on the critical path, the project completion time will most likely increase
 A project has been analyzed using the critical path method (CPM).