Question: A project has been defined to contain the following network and list of activities: What is the probability of completing the project longer than 43

A project has been defined to contain the following network and list of activities:

What is the probability of completing the project longer than 43 days?

Activity

Immediate Predecessor

Time Estimates (days)

Expected Times

Variances

a

m

b

A

-

5

7

9

7.00

0.444

B

-

4

6

8

6.00

0.444

C

A

9

12

15

D

A

9

10

11

10.00

0.111

E

B

9

11

13

11.00

0.444

F

C, D

17

18

19

18.00

0.111

G

E

14

17

20

17.00

1.000

H

F, G

6

8

10

8.00

0.444

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!