Question: A project has been defined to contain the following network and list of activities: 1 MGT 4 2 2 : Production Management table [

A project has been defined to contain the following network and list of activities:
1
MGT 422: Production Management
\table[[Activity,\table[[Time Estimates],[(days)]],\table[[Expected],[Times (ET)]],Variances],[a,m,b],[A,2,3,4,3,0.111],[B,5,8,11,8,1.000],[C,4,5,12,6,1.778],[D,3,4,5,,],[E,1,3,5,3,0.444],[F,1,2,3,2,0.111],[G,2,4,6,4,0.444]]
Determine the probability of completing the project longer than 24 days.