Question: A project has Earned Value ( EV ) of $ 2 5 0 , Actual Cost ( AC ) of $ 2 0 0 and

A project has Earned Value (EV) of $250, Actual Cost (AC) of $200 and Planned Value (PV) of $350. What is the Cost Performance Index (CPI)?
1,25
1,40
0,80
1,05