Question: A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The
A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90% 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWP for Activity D? Multiple Choice Over $20K 50 - SSK $5.01K - STOK $10.01K - 515 $15.01K-$20K