Question: A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The
A project has four activities: A, B, C, and D. The budgeted (planned) cost of each activity is $22K, $14K, $12K, and $28K, respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the cost variance for the project?
rev: 11_12_2020_QC_CS-240638
Multiple Choice
-
Over 1.60K
-
1.00K 1.20K
-
1.41K 1.60K
-
Under 1.00K
-
1.21K 1.40K