Question: A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each
A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:

Activity Time (weeks) Activity Probability 0.31 0.32 0.24 0.13 2 0.24 0.54 0.22 15 17 19 21 23 0.09 0.23 0.39 0.20 0.09 0.73 7 2 0.27