Question: A project has four activities that take 4 , 3 , 6 , and 7 days, respectively. What is the total completion time for the

A project has four activities that take 4,3,6, and 7 days, respectively. What is the total completion time for the project? multiple choice3 days, because this is the minimum time7 days, because this is the maximum time20 days, because this is the sum of the timesIt is not possible to determine the total completion time from the given information