Question: Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 4
Given is a CPM project network diagram as shown below.
Activity
Start
A
B
C
D
E
F
G
H
End
days
a The Project Completion time Question Blank of days.
b The Earliest Start time, ES of Activity G Question Blank of days.
c The Latest Finish time, LF of Activity C Question Blank of days.
d The critical activities are Question Blank of ex Fill in answer as: ABCD