Question: A project has four activities that take 4, 3, 6, and 7 days, respectively. What is the total completion time for the project? multiple choice
A project has four activities that take 4, 3, 6, and 7 days, respectively. What is the total completion time for the project? multiple choice 3 days, because this is the minimum time 7 days, because this is the maximum time 20 days, because this is the sum of the times It is not possible to determine the total completion time from the given information