Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(8.5, 17, 25.5 ),
A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(8.5, 17, 25.5 ), B( 2.5, 5, 7.5 ), C( 4, 4, 4 ), D( 5, 5, 5 ) weeks. What probability would you assign to a project duration of more than 22 weeks