Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(8.5, 17, 25.5 ),
A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(8.5, 17, 25.5 ), B( 6.5, 13, 19.5 ), C( 3, 3, 3 ), D( 4, 4, 4 ) weeks. What probability would you assign to a project duration of more than 30 weeks?
a.
0.7944
b.
1
c.
0.2021
d.
0.5
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
