Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(8.5, 17, 25.5 ),

A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(8.5, 17, 25.5 ), B( 6.5, 13, 19.5 ), C( 3, 3, 3 ), D( 4, 4, 4 ) weeks. What probability would you assign to a project duration of more than 30 weeks?

a.

0.7944

b.

1

c.

0.2021

d.

0.5