Question 28 A project has four major activities.

Question 28 A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(8.5, 17, 25.5), B( 2.5, 5, 7.5), C(4,4,4), D(5,5,5) weeks. What probability would you assign to a project duration of more than 22 weeks? Not yet answered O a. 0.4135 Marked out of 2.00 O b. 0.8231 O c. 1 Remove flag O d. 0.5