Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(6, 12, 18 ),

A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(6, 12, 18 ), B( 6.5, 13, 19.5 ), C( 4, 4, 4 ), D( 4, 4, 4 ) weeks. What probability would you assign to a project duration of more than 25 weeks?

Select one:

a. 0.1609

b. 1

c. 0.9006

d. 0.5