Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(6, 12, 18 ),
A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(6, 12, 18 ), B( 6.5, 13, 19.5 ), C( 4, 4, 4 ), D( 4, 4, 4 ) weeks. What probability would you assign to a project duration of more than 25 weeks?
Select one:
a. 0.1609
b. 1
c. 0.9006
d. 0.5