Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(9, 18, 27), B(

A project has four major activities. Activity A
A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(9, 18, 27), B( 6.5, 13, 19.5), C(1,2,3), D( 14.5, 29, 43.5) weeks. What probability would you assign to a project duration of more than 31 weeks? O a. 0.5 Ob 0.821 O c. 0.75 O d. 0.277