Question: THE SOLUTION TO THIS QUESTION IS POSTED TWICE WITH 2 different answers and solution A project has four major activities. Activity A precedes activity B,

THE SOLUTION TO THIS QUESTION IS POSTED TWICE WITH 2 different answers and solution

A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(6, 12, 18 ), B( 6.5, 13, 19.5 ), C( 4, 4, 4 ), D(4, 4, 4 ) weeks. What probability would you assign to a project duration of more than 25 weeks?

Which one is correct ? This operations management course