Question: THE SOLUTION TO THIS QUESTION IS POSTED TWICE WITH 2 different answers and solution A project has four major activities. Activity A precedes activity B,
THE SOLUTION TO THIS QUESTION IS POSTED TWICE WITH 2 different answers and solution
A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(6, 12, 18 ), B( 6.5, 13, 19.5 ), C( 4, 4, 4 ), D(4, 4, 4 ) weeks. What probability would you assign to a project duration of more than 25 weeks?
Which one is correct ? This operations management course
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
