Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(6, 12, 18 ),

A project has four major activities. Activity A
A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(6, 12, 18 ), B( 3.5, 7, 10.5), C(2, 4, 6), D( 7.5, 15, 22.5) weeks. What probability would you assign to a project duration of more than 19 weeks? e a 0.5 b. 0.374 O c. 0.9 Od 0.75