A project has four major activities. Activity A

A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(6, 12, 18), B( 3, 6, 9), C(1, 2, 3), D( 8, 16, 24) weeks. What probability would you assign to a project duration of more than 18 weeks? Select one: a. 0.881 b. 0.75 C. 0.249 d. 0.5