Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3- point estimates for activities are A(12, 24, 36

A project has four major activities. Activity A
A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3- point estimates for activities are A(12, 24, 36 ), B( 3, 6,9), C( 1.5, 3, 4.5), D( 13.5, 27, 40.5) weeks. What probability would you assign to a project duration of more than 30 weeks? O a. a. 0.378 O b. 0.788 O c.0.75 O d. 0.5