Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(9, 18, 27 ),

A project has four major activities. Activity A

A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(9, 18, 27 ), B( 4.5, 9, 13.5), C( 1.5, 3, 4.5), D( 12, 24, 36 ) weeks. What probability would you assign to a project duration of more than 27 weeks? a. 0.869 b. 0.75 C. 0.171 d. 0.5