Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(3, 6, 9 ),
A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(3, 6, 9 ), B( 5, 10, 15 ), C( 2, 2, 2 ), D( 5, 5, 5 ) weeks. What probability would you assign to a project duration of more than 16 weeks?
Select one:
a.0.3048
b.0.5
c.1
d.0.768