Question: A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(3.5,7,10.5),B(4.5,9,13.5),C(4,4,4),D(3,3,3) weeks. What probability
A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(3.5,7,10.5),B(4.5,9,13.5),C(4,4,4),D(3,3,3) weeks. What probability would you assign to a project duration of more than 16 weeks? a. 1 b. 0.5 C. 0.6083 d. 0.3329