Question: A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost

A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest total cost for completing this project in 33 weeks?
Activity
Normal time
Crash time
Normal Cost
Crash Cost
Predecessor
A
8
5
$1,000
2,000
B
6
4
1,500
2,000
A
C
8
5
1,800
2,300
A
D
12
9
1,000
1,800
B
E
14
11
950
1,450
B
F
9
7
1,500
1,900
C, D
G
7
5
2,300
2,800
E, F
$11,250
$11,500
$12,250
$12,500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!