Question: A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest cotal cost

A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the lowest cotal cost for completing this project in 33 weeks?
\table[[Activity,\table[[Normal],[time]],Crash time,\table[[Normal],[Cost]],\table[[Crash],[Cost]],Predecessor],[A,8,5,$1,000,2,000,],[B,6,4,1,500,2,000,A],[C,8,5,1,800,2,300,A],[D,12,9,1,000,1,800,B],[E,14,11,950,1,450,B],[F,9,7,1,500,1,900,C, D],[G,7,5,2,300,2,800,E, F]]
 A project has the activity duration and cost information indicated in