Question: A project has the following activities: Activity Expected Time Variance Critical? A 3.0 1.4 Yes B 6.5 2.3 No C 5.1 2.0 No D 4.0
A project has the following activities:
| Activity | Expected Time | Variance | Critical? |
| A | 3.0 | 1.4 | Yes |
| B | 6.5 | 2.3 | No |
| C | 5.1 | 2.0 | No |
| D | 4.0 | 1.7 | Yes |
| E | 2.0 | 1.0 | Yes |
All times are in weeks.
The average duration and standard deviation of this project's duration are:
Group of answer choices
20.6 weeks and 1.58 weeks
18.1 weeks and 4.0 weeks
20.6 weeks and 2.9 weeks
9weeks and 2.02 weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts