Question: A project has the following activities: Activity Expected Time Variance Critical? A 3.0 1.4 Yes B 6.5 2.3 No C 5.1 2.0 No D 4.0

A project has the following activities:

Activity Expected Time Variance Critical?
A 3.0 1.4 Yes
B 6.5 2.3 No
C 5.1 2.0 No
D 4.0 1.7 Yes
E 2.0 1.0 Yes

All times are in weeks.

The average duration and standard deviation of this project's duration are:

Group of answer choices

20.6 weeks and 1.58 weeks

18.1 weeks and 4.0 weeks

20.6 weeks and 2.9 weeks

9weeks and 2.02 weeks