Question: A project has the following activities, with specified precedents, expected durations (in days), and crash cost/day. Each activity can be crashed to a minimum duration

A project has the following activities, withA project has the following activities, with

A project has the following activities, with specified precedents, expected durations (in days), and crash cost/day. Each activity can be crashed to a minimum duration of 1 day. (This is the same network as a previous problem.) What is the minimum total cost to shorten the project by 1 day? Round your answers to 2 decimals. Activity Precedent Duration Crash cost/day 3 $350 B A 4.0 $250 $400 D B 6 $150 $200 F C 4 $275