Question: A project has the following activities, with specified precedents, expected durations (in days), and crash cost/day. Each activity can be crashed to a minimum duration

A project has the following activities, with specified precedents, expected durations (in days), and crash cost/day. Each activity can be crashed to a minimum duration of 1 day. (This is the same network as a previous problem.) What is the minimum total cost to shorten the project by 2 days? Round your answers to 2 decimals.

Activity

Precedent

Duration

Crash cost/day

A

-

3

$350

B

A

3.9

$250

C

A

6

$400

D

B

6

$150

E

B

4.1

$200

F

C

4

$275

G

D

6.2

$500

H

E

8

$300

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!