Question: A project has the following activities, with specified precedents, expected durations (in days), and crash cost/day. Each activity can be crashed to a minimum duration
A project has the following activities, with specified precedents, expected durations (in days), and crash cost/day. Each activity can be crashed to a minimum duration of 1 day. (This is the same network as a previous problem.) What is the minimum total cost to shorten the project by 2 days? Round your answers to 2 decimals.
| Activity | Precedent | Duration | Crash cost/day |
| A | - | 3 | $350 |
| B | A | 3.9 | $250 |
| C | A | 6 | $400 |
| D | B | 6 | $150 |
| E | B | 4.1 | $200 |
| F | C | 4 | $275 |
| G | D | 6.2 | $500 |
| H | E | 8 | $300 |