Question: A project has the following characteristics Compute the project completion time and identify the criticalon-critical activities with their slack values. Immediate Activity Duration (days) Predecessors

A project has the following characteristics
Compute the project completion time and identify the criticalon-critical activities with their slack values.
Immediate Activity Duration (days) Predecessors A 1 B A 4 C . 2 D . 2 E D 3 F D 3 G E 2 . F,G 1 1 , 3 J B 2 2Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
