Question: A project has the following network. Suppose that the project starts at time 0 . The crash cost per time unit is shown in the

A project has the following network.
Suppose that the project starts at time 0. The crash cost per time unit is shown in the following table.
What is the cost of crashing the project by 3 time units.
Activities Normal time Crash time Crash cost per time unit
A 2150
B 4260
C 31150
D 31300
E 6580
F 41110

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock