Question: A project has the following network. Suppose that the project starts at time 0. The crash cost per time unit is shown in the following
A project has the following network. Suppose that the project starts at time 0.

The crash cost per time unit is shown in the following table.
| Normal time | Crash time | Crash cost per time unit | |
| A | 2 | 1 | 50 |
| B | 4 | 2 | 200 |
| C | 3 | 1 | 150 |
| D | 3 | 1 | 300 |
| E | 6 | 5 | 80 |
| F | 4 | 1 | 110 |
What is the crashing cost for reducing the project duration by 2 time units?
D F 2 4 -CD :D start E end 0 6 0 3Step by Step Solution