Question: A project has the following network. Suppose that the project starts at time 0. The crash cost per time unit is shown in the following

A project has the following network. Suppose that the project starts at time 0.

A project has the following network. Suppose that

The crash cost per time unit is shown in the following table.

Normal time

Crash time

Crash cost per time unit

A

2

1

50

B

4

2

200

C

3

1

150

D

3

1

300

E

6

5

80

F

4

1

110

What is the crashing cost for reducing the project duration by 2 time units?

D F 2 4 -CD :D start E end 0 6 0 3