Question: A project has the three paths. The paths and three estimated times ( most likely, optimistic and pessimistic are as follows: Expected time: to +
A project has the three paths. The paths and three estimated times most likely, optimistic and pessimistic are as follows:
Expected time: to tm tp
Variance tp to
Path mean sum of expected times on path
Path standard deviation square root of path mean
Z Specified time Path mean path standard deviation
Path XYZ
Optimistic to Most likely tm Pessimistic tp Expected timete
Activity X
Activity Y
Activity Z
Path QRS
Activity Q
Activity R
Activity S
Path TUV
Activity T
Activity U
Activity V
Determine the expected time for each activity X Y Z Q R S T U V
What is the critical path QRS
What is the variance of each activity on the critical path
What is the path standard deviation
What is the probability of completing the project critical path in weeks, and weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock