A project is about placing reinforcing steel into a precast slab. The project manager employs two...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
A project is about placing reinforcing steel into a precast slab. The project manager employs two skilled steel setters (also called "rodmen" on site) and is focused on job clock time, labor productivity and labor cost estimate. Several construction scenarios will be considered. 50 ft. 70 ft. Y direction X direction Steel rebars are used to reinforce a concrete slab on the ground, 50 ft. wide and 70 ft. long. The reinforcing steel is designed as #4 rebars (½ in diameter, 0.668 lb/ft), with no bends. The available rebar stock (rebar purchased from the market) is limited to 30 ft.; rebars need to be cut and overlapped to fit to the slab dimensions (All laps are 18 in.). The rebars are spaced 12 in. apart from each other in both ways. Precast concrete blocks are used to support the slab rebars. Precast concrete blocks are spaced over average 5 ft. but not over 6 ft. apart in both directions, under the intersection points of rebars. The bars will be tied at each intersection by steel setters. All rebars need to be stored in a storage area with about 80-ft. average distance away from the center of the slab. The hourly rate (bare) is $56/hr for each individual steel setter. Rebars can be spliced with 3 rebars arranged in X direction and 4 rebars arranged in Y direction. Important to note: 1. Identical-length rebar segments will be cut for each direction. Rebars on the X direction all have exactly the same length, while their length may differ from the Y direction, all the rebar segments in Y direction are also identical in length. (This would make it easier and less error- prone for the laborers to identify and handle rebars on site) 2. The concrete cover is specified as 0.5 ft., which is the gap from the first rebar center line to the concrete edge; this specification applies to the four edges of the slab. a) Sketch design: You need to calculate the length of rebar installed along each direction; then sketch the rebar laps for both directions; then design concrete block position and plot block placing details. b) Quantity Takeoff & Cutting plan: According to each design alternative, Takeoff the required quantity of rebar in total length (ft.) for both directions. • Takeoff the quantity of intersections and number of ties, and concrete blocks. • Build a cutting plan, based on which, calculate the material cost assuming rebar cost is $1/ft. and also measure the rebar utilization ratio for each scenario. (Hint: Rebar utilization ratio = total design length / total stock length. Note the higher this ratio, the less waste of material). A particular cutting plan consists of cutting patterns and quantity of rebar stocks to be cut by a particular cutting pattern, in order to meet the rebar installation requirements in the field. In providing the cutting plan, you also takeoff the amount of wastage. The cutting plan can be prepared by using the format given below. Cutting Pattern No. 1 2 3 Cutting Pattern Sketch 15% 13.375' 1,625'w Detail Calculation 15'+13.375 +1.625'waste Qty of rebar stocks to be cut 50 Qty of rebar segments produced 15': 50 pcs 13.625': 50pcs *Details in the table are only for demonstration purposes and are not part of the solution. c) Estimate the time required in hours for the following activities: Activity 1: Cutting rebar stocks into rebar segments according to the cutting plan. Two steel setters who work as a team, it needs an average of 30 seconds to cut one rebar stock regardless of the cutting pattern; Activity II: Carrying rebar segments to the slab site, it also needs two steel setters to work as a team: The cycle time required to place the reinforcing includes the time to carry bars to the slab precast site at speed of 100 ft/min, plus the time for the two workers to walk back to the steel stockpile with the speed of 100 ft/min; plus a total of 1 min for picking up and putting down reinforcing. The two workers can carry 6 bars in each trip (rebar segments resulting from cutting, which are counted regardless of the specific length of a rebar segment). Activity III: Placing the bars (rebar segments) on blocks and spacing them: the two persons working together can place 2 bars/min. Activity IV: Tying the bars (rebar segments) at intersections: Each person can make 5 ties per min. Consider a 45-min per hour efficiency and estimate total working time in hours for rebar handling and installation. Finish-to-Start logical relationships are imposed between Activity II and Activity I; Activity III and Activity II; Activity IV and Activity III. d) According to material cost and labor cost, calculate total construction cost. Material Cost (S) Labor Cost (S) Total Cost (S) A project is about placing reinforcing steel into a precast slab. The project manager employs two skilled steel setters (also called "rodmen" on site) and is focused on job clock time, labor productivity and labor cost estimate. Several construction scenarios will be considered. 50 ft. 70 ft. Y direction X direction Steel rebars are used to reinforce a concrete slab on the ground, 50 ft. wide and 70 ft. long. The reinforcing steel is designed as #4 rebars (½ in diameter, 0.668 lb/ft), with no bends. The available rebar stock (rebar purchased from the market) is limited to 30 ft.; rebars need to be cut and overlapped to fit to the slab dimensions (All laps are 18 in.). The rebars are spaced 12 in. apart from each other in both ways. Precast concrete blocks are used to support the slab rebars. Precast concrete blocks are spaced over average 5 ft. but not over 6 ft. apart in both directions, under the intersection points of rebars. The bars will be tied at each intersection by steel setters. All rebars need to be stored in a storage area with about 80-ft. average distance away from the center of the slab. The hourly rate (bare) is $56/hr for each individual steel setter. Rebars can be spliced with 3 rebars arranged in X direction and 4 rebars arranged in Y direction. Important to note: 1. Identical-length rebar segments will be cut for each direction. Rebars on the X direction all have exactly the same length, while their length may differ from the Y direction, all the rebar segments in Y direction are also identical in length. (This would make it easier and less error- prone for the laborers to identify and handle rebars on site) 2. The concrete cover is specified as 0.5 ft., which is the gap from the first rebar center line to the concrete edge; this specification applies to the four edges of the slab. a) Sketch design: You need to calculate the length of rebar installed along each direction; then sketch the rebar laps for both directions; then design concrete block position and plot block placing details. b) Quantity Takeoff & Cutting plan: According to each design alternative, Takeoff the required quantity of rebar in total length (ft.) for both directions. • Takeoff the quantity of intersections and number of ties, and concrete blocks. • Build a cutting plan, based on which, calculate the material cost assuming rebar cost is $1/ft. and also measure the rebar utilization ratio for each scenario. (Hint: Rebar utilization ratio = total design length / total stock length. Note the higher this ratio, the less waste of material). A particular cutting plan consists of cutting patterns and quantity of rebar stocks to be cut by a particular cutting pattern, in order to meet the rebar installation requirements in the field. In providing the cutting plan, you also takeoff the amount of wastage. The cutting plan can be prepared by using the format given below. Cutting Pattern No. 1 2 3 Cutting Pattern Sketch 15% 13.375' 1,625'w Detail Calculation 15'+13.375 +1.625'waste Qty of rebar stocks to be cut 50 Qty of rebar segments produced 15': 50 pcs 13.625': 50pcs *Details in the table are only for demonstration purposes and are not part of the solution. c) Estimate the time required in hours for the following activities: Activity 1: Cutting rebar stocks into rebar segments according to the cutting plan. Two steel setters who work as a team, it needs an average of 30 seconds to cut one rebar stock regardless of the cutting pattern; Activity II: Carrying rebar segments to the slab site, it also needs two steel setters to work as a team: The cycle time required to place the reinforcing includes the time to carry bars to the slab precast site at speed of 100 ft/min, plus the time for the two workers to walk back to the steel stockpile with the speed of 100 ft/min; plus a total of 1 min for picking up and putting down reinforcing. The two workers can carry 6 bars in each trip (rebar segments resulting from cutting, which are counted regardless of the specific length of a rebar segment). Activity III: Placing the bars (rebar segments) on blocks and spacing them: the two persons working together can place 2 bars/min. Activity IV: Tying the bars (rebar segments) at intersections: Each person can make 5 ties per min. Consider a 45-min per hour efficiency and estimate total working time in hours for rebar handling and installation. Finish-to-Start logical relationships are imposed between Activity II and Activity I; Activity III and Activity II; Activity IV and Activity III. d) According to material cost and labor cost, calculate total construction cost. Material Cost (S) Labor Cost (S) Total Cost (S)
Expert Answer:
Related Book For
Vector Mechanics for Engineers Statics and Dynamics
ISBN: 978-0073212227
8th Edition
Authors: Ferdinand Beer, E. Russell Johnston, Jr., Elliot Eisenberg, William Clausen, David Mazurek, Phillip Cornwell
Posted Date:
Students also viewed these civil engineering questions
-
A project is about placing reinforcing steel for a cast-in-situ footing. The project manager needs to plan job clock time, labor productivity and labor cost estimate by employing two skilled steel...
-
Explain how budgets are used to reinforce organizational belief systems.
-
A precast concrete wall section is temporarily held by two cables as shown. Knowing that the tensions in cables BD and FE are 900 N and 675 N, respectively, determine the moment about point O of the...
-
Three balls A, B, and C, with masses of 3 kg, 1 kg, and 1 kg, respectively, are connected by massless rods. The balls are located as in Figure. What are the coordinates of the center ofmass? y. m 1...
-
Some say that an ERP will change Benton's culture. How do you respond to this concern?
-
Indicate where the following items would ordinarily appear on the financial statements of Boleyn, Inc. for the year 2015. (a) The service life of certain equipment was changed from 8 to 5 years. If a...
-
What are the ways an organization sustains its culture.
-
Johns Exteriors produces exterior siding for homes. The Preparation Department begins with wood, which is chopped into small bits. At the end of the process, an adhesive is added. Then the...
-
The law subjects disability discrimination to a special set of rules. Why? Should other kinds of discrimination garner such treatment? Why or why not?
-
A load of lumber er weighing W = 25 kN is being raised as shown by a mobile crane. Knowing that the tension is 25kN in all portions of cable AEF and that the weight of boom ABC is 3kN, determine (a)...
-
Question 2: Mirbat Company has the following information for the period ended 31 December 2020. Direct material purchases OMR 380000 Direct labor OMR 210000 Factory maintenance Power and heat-factory...
-
You are now a business analyst for Global Bike Inc. (GBI). You have been assigned to assist the strategic planning team with profitability analysis and forecasting. Your IT team has pulled...
-
2. The following code snippets contains bug(s). Find and correct them. (2X1 = 2 pts) a) When this code snippet is executed, it should assign 10 to the array element that corresponds to the third row...
-
3. What is the output of the following program ? (2pts) = int Alpha [6] [600, 500, 400, 300, 200, 100}; int i; for (i=5; i > 0; i--) cout < < Alpha[i] < < 4. Given a 5000-element integer array...
-
Suppose a bank has a large data set containing data for 10000 customers, and each customer appears in the data set exactly one time. The data set was created on October 1, 2023, and contains the...
-
Tesla's (TSLA) 10-K (annual report) for the year ended December 2022, their proxy materials for the shareholder meeting in 2023, and amended 10-K for 2022 filed in 2023. How does Tesla make money?...
-
There are 166 physicians practicing in Port St. Lucie. Of them, 83 are female and 28 are dermatologists (total). Of the 83 female physicians, 14 are dermatologists. Suppose one physician from Port...
-
Heineken N.V., a global brewer based in the Netherlands, reports the following balance sheet accounts for the year ended December 31, 2016 (euros in millions). Prepare the balance sheet for this...
-
A slender rod AB of negligible mass is attached to two collars A and B that can move freely along the guide rods shown. n. Knowing that β =30°, P = 100 N, and Q = 25 N, determine the value...
-
Neglecting the size of the pulley at G, (a) Draw the shear and bending-moment diagrams for the beam AB, (b) Determine the maximum absolute values of the shear and bending moment. 24 in. 16 in. 48 in....
-
A heavy crate is being moved a short distance using three identical cylinders as rollers. Knowing that at the instant shown the crate has a velocity of 200 mm/s and an acceleration of 400mm/s2, both...
-
From the following data, construct the sales ledger control account for the month of November 2018. Balances of trade receivables at 1 Nov 2018 Balances of trade receivables at 30 Nov 2018 For the...
-
From the following data, construct the sales ledger control account for the month of January 2017. Balances of trade receivables at 1 Jan 2017 Balances of trade receivables at 31 Jan 2017 For the...
-
From the following data, construct the sales ledger control account for the month of June 2012. Balances of trade receivables as at 1 June Balances of trade receivables as at 30 June For the month of...
Study smarter with the SolutionInn App