Question: A project is broken into the tasks shown in the following table along with the dependencies, duration and the need staff size for each task.

A project is broken into the tasks shown in the

A project is broken into the tasks shown in the following table along with the dependencies, duration and the need staff size for each task. Task Duration (Day) Dependency Staff A 2 3 B 4 A 2 6 A 4 D 4 A 3 E 5 B 4 F 7 2 B,C D.E.F G 3 4 1. Build the Gantt chart to calculate the requested duration to finish the project in addition to the needed staff size. (15 points) | Task 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 A B D E F G Staff